2013 Bond Information
Clear Lake Intermediate

15545 El Camino Real
 Houston, Texas 77062 

Original Building Completed: 1972
Building Area: 150,815
Building Capacity: 1,076

Built in 1972, Clear Lake Intermediate’s existing woodworking shops would be renovated to also include an engineering and technology lab to reflect the District’s focus on college and career readiness programs. The recommendation is to also renovate aging locker rooms and food lab and refurbish the elevator. 


Bond Proposal: $ 4,886,194
  • Classroom conversions to accommodate CTE educational programs 
  • Replace elevator 
  • Improve locker rooms 
  • Add security fencing around portable classrooms 
  • Replace major components of AC/heating system 
  • Replace intercom system, including clocks 
  • Replace sound system for competition gym 
  • Replace major components of fire alarm system 
  • Improve site drainage 
  • Replace exterior walkway canopies 
  • Improve athletic facilities for student safety 
  • Install fireproof stage curtains